Carat (^) Symbol Next To The Price/Unit

You might have noticed a  carat symbol next to your Price/Unit when you are assigning resources or roles. This usually happens because of following reasons: 1) Role has been assigned to the activity When Role is assigned to the activity Price/Unit is taken from the default settings of the project.

Continue Reading ...

Space Between Actual Bar And Remaining Bar for In-Progress Activities

While updating your progress on a project have you ever notice a gap in your activity bar in Gantt chart? It can be because of the following reasons : 1) Data date of the project is earlier than the Remaining Start date of the activity (which doesn’t happen that often) 2) Using Retained logic and […]

Continue Reading ...